In under 2 weeks Porter Davis have completed the Slab/Base and commenced on our Frame. 


Demolition completed.


Site Scrape, Plumping and Electricity Meter installed all in one week (Aug 3 - Aug 7)



Aug 10 - Steel Piles and Waffles etc set up.   Aug 11 - Slab Pour Completed.

Frame commences today Aug 13. Porter Davis are moving a lot quicker than what I anticipated.