Hope everyone has been enjoying the festive season and making most of their time off. PD have a 2 week shutdown period which ends today but I somehow find it hard to believe that our tradies will be back into the full swing of things until next week. So we managed to get inside through an unlocked door and took a heap of snaps of the house. It is progressing nicely I must say.
So to end off 2015 we can also tick off
- Bathroom tapware, showers and mirrors installed
- Tiling looks to be 95% complete. The grout work is questionable though.
- Garage walls plastered
- Electrical fit out nearly completed
- Alfresco drain fitted
- Wall under the staircase frame work commences
- External rendering completed
- Garage doors fitted
| Kitchen Sink: Teknobilli Oz T7 300 pull out sink mixer Upgrade cost $328 |
| Downstairs Bathroom: Nikles Fresh twin rail shower & Como Grey Tiles Upgrade cost $310 |
| Shower exhaust fan (standard) We also upgraded to have the tiles go all the way to the ceiling. |
| Master Ensuite Double Vanity Mizu soothe chrome basic mixer (Upgrade $46 each) and Kado arc inset basin (Upgrade $24 each) |
| Heatastic light heater thingy in the bathroom Honestly I don't even remember agreeing to this one as it's something you can do after handover cheaply. |
| Alfresco drainage |
| Wardrobe Fitouts |
| Bedroom 2 Walk in Robe |
| Upstairs Linen |
| I believe this is the heating vent which is located outside the Master Room which I think is a bit odd. Something I did not check during Tender/Contracts. |
![]() |
| Completely missed this during tender. Its a frequented walk area so I would have preferred it somewhere else. Not sure if it could have been changed but I wish I asked. |
| Staircase lighting with sensors |
| Can't wait to see it light up |
| External water tap. |
| Rendering to whole house is finally done. |
| Render colour is dulux champignon |
| Mouldings still need to be painted a shade lighter than the render (Colour Doe) |