TIMELINE
2014
APRIL - SEPTEMBER 2014 - House Hunting and lots of researchOCTOBER 2014 - Initial Deposit Paid with Sales Consultant
NOVEMBER 2014 - Colour,Tender and Contracts Appointment Booked, Loan Pre-approved.
DECEMBER 2014 - Colour Selections Completed
2015
FEBRUARY 2015 - Tender PresentationMARCH 2015 - Contract Appointment
APRIL 2015 - Contract Signed, Services Abolished, Electrical Underground Pitt Installed,
MAY 2015 - Gas and Electricity Abolished
JUNE 2015 - Loan approved
EARLY JULY 2015 - Home Demolished, Survey and Second Soil Test Completed
31 JULY 2015 - Site Scrape, Rubbish and Portaloo Delivered
3 AUGUST 2015 - Excavation and Slab
7 AUGUST 2015 - Plumbing In
11 AUGUST 2015 - Slab pour/Slab Completed
13 AUGUST 2015 - Frame Commencement
26 AUGUST 2015 - Windows Delivered
28 AUGUST 2015 - Frame Completed
3 SEPTEMBER 2015 - Gutters Fascia Completed
4 SEPTEMBER 2015 - Roof Completed
11 SEPTEMBER 2015 - House wrapped
18 SEPTEMBER 2015 - Hebel Delivered
21 SEPTEMBER 2015 - Hebel Installation Commences
25 SEPTEMBER 2015 - Ground floor Hebel completed
1 OCTOBER 2015 - Hebel Completed, External Doors Installed
5 OCTOBER 2015 - Lock up
8 OCTOBER 2015 - Eaves installation commences
9 OCTOBER 2015 - Plaster and External rendering commences
16 OCTOBER 2015 - Cornices, Stairs Installed
27 OCTOBER 2015 - Fixing Stage Completed, Garage and Alfresco Roof commences
12 NOVEMBER 2015 - Practical Completion Commences - Internal painting starts
18 NOVEMBER 2015 - External rendering continues
20 NOVEMBER 2015 - Essastone benchtops installed, Waterproofing of wet areas
24 NOVEMBER 2015 - Rendering to first floor
1 DECEMBER 2015 - Tiling, Internal door hardware fitted, Linen, pantry, galley shelves fitted
9 DECEMBER 2015 - Alfresco roof installed
12 DECEMBER 2015 - Electrical down lights and switches fitted, heating/cooling vents installed
16 DECEMBER 2015 - Garage walls plastered, tapware, bathtub, showers and mirrors installed,
18 DECEMBER 2015 - Wall under stairs fix commences, External rendering completed
21 DECEMBER 2015 - Garage doors installed.
2016
5 JANUARY 2016 - Wall/cornice under the staircase FIXED
14 JANUARY 2016 - Alfresco, garage, bathroom ceilings painted
15 JANUARY 2016 - Remaining internal walls painted
18 JANUARY 2016 - Stairs stained, external door painted
19 JANUARY 2016 - House clean
19 JANUARY 2016 - Internal sealants, Render touch ups
20 JANUARY 2016 - Mouldings install to front upper window
28 JANUARY 2016 - PCI, Independant Inspection
4 FEBRUARY 2016 - Handover
5 FEBRUARY 2016 - Appliances & Hot Water Installed, Floorboards installed
10 FEBRUARY 2016 - Carpets installed
23 FEBRUARY 2016 - Driveway sealed and side fence and gate installed